Powergrid Corp of India has successfully commissioned the Vindhyachal Pooling Station-Jabalpur Pooling Station 765kV Double Circuit Transmission line in 2018. The project one of the longest transmission lines comprising more that more than 750 circuit km traverses through seven districts in Madhya Pradesh.
Now, it strengthens the transmission network and improves reliability and security. The project was is part of the Transmission System Strengthening associated with Vindhyachal-V and has been established on a Build, Own, Operate and Maintain (BOOM) basis.
Company Profile : Powergrid Corp Ltd
Leave a Reply